1.1 This AIRAC AIP Supplement provides advance information on the implementation of the airside works associated with the Terminal Expansion Project at Tawau Airport (WBKW), including the temporary operational arrangements and restrictions applicable during the construction period.
2.1 The Terminal Expansion Project comprises landside terminal reconfiguration works and associated airside aircraft stand reconfiguration works. This AIP Supplement addresses only the airside works that affect aircraft operations.
2.2 The Airside Aircraft Stands Reconfiguration works comprise:
Relocation of Utilities.
Passenger Boarding Bridge installation.
Parking bays reconfiguration.
Associated civil, mechanical and electrical works.
3.1 The work will be implemented in the following stages:
Table 1: Major Construction Activities
| Stage | Period | Major Activities |
|---|---|---|
| Stage 1: Enabling works – Relocation of utilities within the Ground Service Road corridor | 22nd June 2026 to 30th September 2026 |
|
| Stage 2A: Installation of new Passenger Boarding Bridges and ramps within the existing area of Bays 3, 4, 5 and 6 | 01st October 2026 to 30th March 2027 |
|
| Stage 2B: Replacement and installation of new Passenger Boarding Bridges and new ramp within the existing area of Bays 1 and 2 | 01st April 2027 to 28th February 2028 |
|
4.1 Throughout the construction period:
Table 2: Aircraft Operational Restrictions and Temporary Measures During Construction
| Stage | Construction Activities | Operational Restrictions | Temporary Operational Measures |
|---|---|---|---|
| Stage 1 | Relocation of utilities within the Ground Service Road corridor – please refer Attachment ‘1’ and Supplementary Attachment “A”. The existing GSE Road will be temporarily re-channelized throughout Stage 1. |
|
|
| Stage 2A – Bay 3,4, 5 and 6 works | Construction works affecting the existing Bay 3, Bay 4, Bay 5 and Bay 6 areas – please refer Attachment ‘2’ and Supplementary Attachment “B” (Installation of new Passenger Boarding Bridges and ramps). Existing Bay 3, Bay 4, Bay 5 and Bay 6 shall be closed and unavailable for aircraft operations. Temporary aircraft parking positions will be established behind the cordoned construction area. |
|
|
| |||
| Stage 2B - Bay 1 and 2 works | Construction works affecting the existing Bay 1, 2 & 3 areas – please refer Attachment ‘3’ and Supplementary Attachment “C” (Installation of new Passenger Boarding Bridge and ramps, and replacement of the existing Passenger Boarding Bridges and ramps) |
|
|
| Existing Bay 1 & 2 shall be closed and unavailable for aircraft operations. Temporary aircraft parking positions will be established behind the cordoned construction area. |
|
5.1 The following safety measures shall be implemented throughout the construction period:
Work Area Demarcation: Construction areas shall be segregated from operational areas using temporary hoardings and illuminated low-height barriers.
Temporary Airside Markings: Temporary aircraft stand markings, apron safety lines, GSE road markings and associated guidance markings shall be provided in accordance with approved staging drawings.
Construction equipment and temporary structures shall remain within the approved obstacle limitation requirements throughout all stages of the work.
Access Control: Access into construction areas shall be controlled and restricted to authorized personnel only.
Foreign Object Debris (FOD) Management: Regular inspection and removal of Foreign Object Debris (FOD) shall be undertaken within operational areas adjacent to the works.
Aircraft and Vehicle Coordination: Construction activities adjacent to operational areas shall be coordinated with Airport Operations and Air Traffic Services.
Emergency Access: Emergency vehicle access to Aircraft Rescue and Fire Fighting (ARFF) services shall be maintained throughout all construction stages.
Operational Lighting and Signage: Temporary lighting, and warning signs shall be provided where required.
Daily Operational Coordination: Daily operational coordination meetings shall be conducted between Airport Operations, Air Traffic Services, Airlines, Ground Handlers and the Contractor.
6.1 Pilots, aircraft operators, ground handling agents and all airside users shall exercise caution when operating within the vicinity of the construction areas and shall comply with all temporary markings, signage, operational instructions and ATC directions.
7.1 For further information, please contact:
| Name | : | Mr. Tadjuddin Bin Tanjing |
| Designated | : | Airport Manager |
| Telephone | : | 019-8837844 |
| : | tadjuddin@malaysiaairports.com.my | |
| Name | : | Mr. Mohd Roslan Bin Sarip |
| Designated | : | Main Contractor |
| Telephone | : | 019-2695026 |
| : | roslan.sarip@azamjaya.my |
8.1 This AIRAC AIP Supplement will remain in force until 28th February 2028 EST. Any updates, changes, or cancellation to this supplement will be notified through NOTAM.